Precast concrete parts for the logistics buildings of Rewe trade Group

The Rewe Group, a leading European trading company, has been committed to the implementation of a comprehensive sustainability concept for some time as expressed, for example, in the first-ever supermarket in Germany erected as a “green building.” The logistics infrastructure of the Group is now also undergoing modernization under this aspect. Among the latest building blocks are two new logistics centers in the Upper Bavarian Eitting and in Oranienburg near Berlin in Germany. The implementation of the projects with a volume totaling around €64 million was entrusted to the precast concrete specialist Klebl of Neumarkt as general contractor. The company is one if the top 20 building contractors in Germany and ranks first in the manufacture of structural precast components.

More than 5,500 precast parts

For the Etting logistics center, Klebl manufactured some 2,600 precast concrete parts, in addition to processing 11,800 m³ of fresh concrete and 1,100 t of steel, produced in its plants in Neumarkt and Penning, transported to the construction site in nearly delivery 1000 trips. The logistics center offers 33,000 m2 of storage and on 7,000 m2 office space on three above-ground floors and one basement floor.

The design of the Group’s national warehouse in Oranienburg, where its full product line is stored, follows the same principle – if to a larger scale: The building of 350 m length, 150 m width and a height of over 16 m is equipped with 124 dock levelers and contains three floors with a volume of 860,000 m³. The building logistics, provided by Klebl via its plants in Frankenförde, Gröbzig and Rinteln, was accordingly complex. From there, more than 3,200 precast parts with a total weight of 31,400 t were delivered to the construction site just in time in more than 1,400 trips.

x

Related articles:

Issue 01/2014 Peikko

Precast parts for logistics hall of GVZ Ingolstadt

At the logistics center at the cargo transport center of the Ingolstadt Betreibergesell-schaft mbH (LGI), in which the German city of Ingolstadt and Audi AG participate equally, the construction of a...

more
Issue 04/2019

Klebl and Dicad – no BIM without process integration

The Klebl Company Group is a medium-sized family enterprise for construction, structural precast components and trade, which is based in Neumarkt in the Upper Palatinate region of Germany. It employs...

more
Issue 07/2009 Industrial construction with precast elements

Klebl builds Europe‘s largest paperworks

The construction is an outstanding exercise in logistics: the site has five fixed cranes, five caterpillar cranes and a number of mobile cranes with a load capacity of up to 750 t. As many as 300...

more
Issue 02/2024 LEHDE

Soest building construction specialist delivered 900 precast elements

Following the demolition of the former department store Dieler in Menden in the German state of North Rhine-Westphalia, the newbuild presents a challenge in terms of material logistics and...

more
Issue 02/2013

The implementation of European standards in Germany

Construction standards establish uniform specifications of product characteristics, test methods to determine such characteristics, actual construction works and the design of buildings and...