Elbe Decken

Solid floor slab as special product for heavy loads

In February 2016, the extensive GWH Riedberg 2.0 project in Frankfurt am Main, Germany, was completed on schedule by the developer GWH Bauprojekte GmbH. The 71 barrier-free apartment, ranging from 66 to 149 m² in size, were built as passive houses. For the construction of the underground garage with 71 parking spaces below the vegetated courtyard, prestressed concrete floor slabs from the company Elbe Delcon GmbH were used for constructing the loadbearing foundation for the landscaped garden above.

The company Indeco GmbH, which specializes in modular building, had awarded Elbe the contract for design, manufacture, and delivery of the floor elements. The building complex with a residential floor space of 6,800 m2 was built by Jöst Bauunternehmen GmbH as general contractor.

Loads of up to 5 t/m² to ­support

For planting the courtyard with trees, it was necessary to provide the roof of the underground garage with a soil cover of at least 1 m. The prestressed concrete floor slabs in the underground garage were required to support weights of up to 2.6 t/m², and in some areas as much as up to 5 t/m². Dipl.-Ing. Thomas Münz-berg, structural engineer with Elbe Delcon GmbH, developed a special solution for this project: “The Elbe solid concrete slab is designed to support extreme loads in industrial buildings with extraordinarily demanding requirements for loadbearing capacity and span lengths, as well as for noise protection.” The solid floor slabs of 30 cm thickness and spans of more than 6 m rarely require columns; in addition, thicker in-situ concrete floors and double-T-beams were not necessary. A total of 278 prestressed concrete floor elements were manufactured for the required surface with a total of 1,727 m2.

Horst Jungmann of the building contractor Jöst Bauunternehmen pointed out: “The use of solid prestressed concrete floor slabs, moreover, had a positive effect on the time factor. For installing all these floor slabs, we needed less than one week during the tight construction schedule. The prestressed concrete floor slabs arrived at the construction site at intervals of 30 to 45 minutes.” For this project, Elbe solid floor slabs from the EMD production series were used.

Related articles:

01/2018 Elbe Decken

Opportunities for precast prestressed concrete floor slabs in building projects

In many European countries, like Belgium or the Netherlands, up to 70 % of all building projects are implemented by means of precast prestressed concrete floor slabs in the meantime. Despite their...

more
07/2015 Elbe Decken

Short construction times thanks to precast prestressed concrete floor units

The Wellnesshotel construction project near Frankfurt am Main of the Stork Hotels & Thermen Group based in Paderborn has an investment sum of around 12 million euros. At Niederhofheimer Strasse in...

more
05/2015 Elbe Decken

Jumbo concrete floors with unsupported spans of more than 16 m

At the beginning of 2015, a new construction project of the Dresden private all-day secondary school was completed by the owner/developer, the IBB Institute für Bildung und Beratung GmbH, completing...

more
05/2017 Unitechnik

Control engineering modernized

Elbe Decken, with 20 production lanes, a storage capacity over more than 45,000 m2 and an annual production capacity of 500,000 m2, is one of Germany’s leading suppliers of precast prestressed...

more
03/2011 Parking garage made with prestressed floor slabs

An ambitious project at Audi AG

The elaborate overall concept required a number of extraordinary measures. For instance, it was required not to disturb the traffic flow of the district road going past the factory. Today, two new...

more