Hybrid structures of precast concrete components and superimposed steel tube tower are economical for very tall wind turbines. The Tubularis PCC Tower concept is suitable for the international wind market and relies on small-format precast concrete components that can be manufactured in non-specialized plants close to the construction site. The Mainz University of Applied Sciences developed the concept of segment joints.

1. Introduction

Wind energy is the driving force in the implementation of the energy revolution and already produced 49% of total renewable energy in 2017. In the process, they ensure 16% of gross electricity generation in Germany. Onshore wind energy accounts for 83% of the wind energy produced [1][2]. The average hub height of newly installed wind turbines throughout Germany amounted to 129.1 m in 2017. On average, these turbines were equipped with a rotor diameter of 113.8 m and provided an output of 2.9 MW [3].

The experience of the last years has shown that the energy yield with increasing...

Related articles:

Issue 02/2014 In a monolithic and segmental construction method

UHPFRC beams with hollow box cross-section

Background Contrary to the monolithic design, for segment construction single building units are prefabricated in the precast concrete factory for later assembly at the construction site. Using joints...

more
Issue 02/2014 Design for biaxial loading or circular sections

Shear design of reinforced-concrete components –

Both on a national and international scale, the shear design of reinforced-concrete components with shear reinforcement currently relies on planar truss models. This analysis has to verify sufficient...

more
Issue 08/2017

Lattice girder floor slabs – tested application as a point-supported slab

To verify the load-bearing capacity of buildings or structural components, the planning engineer uses engineering models. These are secured – in particular in the case of construction with reinforced...

more
Issue 04/2018 SUBMITTED BY/EINGEREICHT VON: R-TECH

R-Tech loading/unloading systems – new load-dropping pallet

R-Tech, the company based in Willendorf-Strelzhof in Austria, has been manufacturing  transport racks for the precast concrete industry since 1998. R-Tech entered the load-dropping pallet it...

more
Issue 02/2017 Lattice girders under cyclic loading

Fatigue of semi-precast slabs

Due to the high efficiency and flexibility of semi-precast slabs with lattice girders compared to in-situ concrete structures, the use of these slab systems increase in building and industrial...

more