Preliminary tests and prototype

Towers for wind turbines comprised of double-wall elements

The energy transition requires electricity to be generated from renewable sources such as wind power. In the foreseeable future, there will be a scarcity of potential high-yield onshore generation sites, which is why a growing number of wind turbines will have to be erected in lower-yield areas. To achieve acceptable energy yields in these regions, wind turbines that are usually erected as tower structures must have large hub heights. Thus, the associated increased dynamic loading makes fatigue a key design criterion.

Hybrid construction methods have become the state of the art for erecting...

Related articles:

Issue 2017-01

Method of constructing a tower of concrete segments

(11) EP 3 095 569 A1 (22) 04.02.2015 (43) 23.11.2016 Bulletin 2016/47 (57) Method of constructing a tower with concrete tower segments. After casting and hardening of a first tower segment, a second...

more
Issue 2014-02 Efficient electric power generation

Hybrid towers for wind power plants in precast construction –

Large wind power towers measuring up to far over 100 m in height are of crucial significance for efficient wind exploitation and electric power generation. Towers of these dimensions are virtually...

more
Issue 2018-06

Structural concrete tower and assembly method

(10) W02018068117 A1 (22) 10.10.2017 (43) 19.04.2018 (57) A structural concrete tower and assembly method, said tower comprising the superpositioning of a first (21) and a second (22) tower segment,...