Five Potain Cranes from the Uperio fleet support complex urban construction projects in Marseille
A fleet of five Potain tower cranes – consisting of two MDT 269 models and three MDT 319 models – is supporting the construction of the “Mistral” project in Marseille, France – one of the largest construction projects currently underway in southeastern France.
The project involves the construction of a 30,000 m² real estate complex and a multi-story parking garage in a densely built-up urban area. The construction project, led by BEC Construction Provence, a subsidiary of Fayat Bâtiment, is characterized by exposed concrete facades, wall panels up to 8 m high, and the extensive use of precast elements – all of which require carefully planned and executed lifting operations.
To meet these challenges, Uperio, a specialist in tower cranes, supplied the five Potain cranes. Each crane is equipped with a 45-meter-long boom and stands on a 4.5-meter- or 6-meter-wide foundation. Hook heights range from 42.3 meters to 60.6 meters, with the tallest MDT 319 installed on a reinforced 6-meter foundation.
The cranes were equipped with various features designed to enhance safety and productivity, including Geda 2PK mast hoists, collision avoidance systems, aviation warning lights, and construction site monitoring technology. All cranes are also equipped with cameras to improve visibility during operation.
One of the biggest challenges on the construction site was operating multiple cranes in a confined urban environment where interference between the machines is inevitable. To address this issue, engineers from BEC Construction Provence, Uperio, and Manitowoc’s Lift Solutions team collaborated to determine the optimal crane positions, hook heights, and configurations before assembly began. Three of the cranes – two Potain MDT 319s and one Potain MDT 269 – received additional technical support from specialists at Manitowoc Lift Solutions to ensure that the configurations met the operational and structural requirements of the construction site.
All five cranes were erected in just two days
“The Mistral project highlights the value of close collaboration between Manitowoc, Uperio, BEC Construction Provence, and our customers,” said Eric Delbecq, Sales Manager at Uperio France. “By combining the technological excellence of Potain cranes with the operational expertise of our teams, we are able to support our customers on the most demanding projects and provide them with reliable, high-performance lifting solutions that are perfectly adapted to the structural conditions of the construction site.”
Despite the project’s complexity, Uperio completed the installation of all five cranes in just two days, helping to keep the project on schedule while overcoming the logistical challenges of a high-traffic urban construction site. The Mistral project is scheduled for completion in January 2028.
“With nearly 800 cranes in operation, Uperio France is one of Potain’s leading strategic partners in the country. The success of large-scale construction projects such as the Mistral project requires close collaboration and a high level of technical support. Potain provides Uperio with this support through readily available spare parts, technical expertise, and customized technical solutions developed by our ‘Lift Solutions’ department.The synergy between the performance of Potain cranes and the operational expertise of the Uperio teams continuously contributes to the success of projects and to Potain’s strong reputation in France,” said Gaël Veillard, Commercial Director for Tower Cranes at Manitowoc in France.
CONTACT
The Manitowoc Company, Inc.
One Park Plaza
11270 West Park Place – Suite 1000
Milwaukee, WI 53224, USA
+1 414 760 4600