Putzmeister Holding GmbH

Doha: Giant project for 2022 FIFA World Cup

The long initial stage up to the 2022 FIFA World Cup and the new alignment of the master plan „Qatar National Vision 2030“ encouraging investments into the future of the country gave rise to more doubts regarding the fact whether the optimism of the last years was realistic at all. Projects such as the new international airport of Doha scheduled to open these days, the currently large number of infrastructure contracts and the huge new port project of Doha show that the State of Qatar really wants to make a difference.

The existing port in the center of the city is regarded as the greatest bottleneck to an economic development of the country. Once the new port being four times larger is completed, Qatar will finally be in the position to meet its obligations to provide the stadiums, hotels and infrastructure FIFA requires for the 2022 World Cup. The annual cargo handling capacity will then be equivalent to 6 million 20ft. containers.

35,000 concrete blocks

„The government wants this project to become one of the major projects in the Gulf region,“ says Khalid Ali, project manager of Fahad Bin Abdulla Ready Mix (FBA, see p. 10 of „The Fahad Bin Abdullah Group of Companies“). FBA is a sub-contractor responsible for supplying and casting of 4 million cubic meters of concrete.

Precast concrete elements are used, among others, for the construction of the 8 km long quay wall, furthermore for the construction of a concrete wall for a pier and for the construction of the breakwater wall protecting the vessels in the port.

According to the project manager Ali, casting 3 million cubic meters of precast blocks will take three years. Just the quay wall requires 1.8 million cubic meters. The first precast block for the quay wall was installed in July 2012. A total of 35,000 blocks will be needed for the new wall, each one weighing in the range of 40 to 90 t.

On the area near the coast, the 2 m high blocks are properly positioned in rank and file. Each block has a „nose“ at the top and a corresponding recess at the bottom enabling the wall to be erected like a large Lego construction. The hollow spaces are filled with spoil.

A batching plant comprising two Sany 180 Eco units is mixing the concrete for the blocks. From 2014, it will also supply the concrete required for the construction of the football area „Doha Stadium“.

Belt conveyor instead of a pump

The blocks are manufactured in individual molds. For this purpose, FBA applies the Telebelt of Putzmeister for the first time in Qatar. Four TBS 130 are used in total at the construction site. The machine made in the USA and Germany ideally fits for this job because it uses a belt conveyor instead of a pump for the placing of concrete. Bulk concrete that is not pumpable can also be placed efficiently and fast in this way. The conveying capacity adds up to 275 m³ concrete per hour.

Once the Telebelt has been put into operation, its advantages soon become obvious. The ready mix trucks arrive in convoy and alternate without interruption just requiring a short set-up time at the feeding hopper. The Telebelt is operated by means of a radio remote control similar to a concrete pump.

Concrete placement is always concerned with fastness. The Telebelt fills the formwork quickly. Directly at the installation site, the concreting team provides for as consistent hardening of the concrete as possible. If a block is finished, the conveyor belt moves 180 degree to an empty form at the opposite side and the concreting process starts again.

x

Related articles:

Issue 03/2019

Football stadiums for Qatar and the 2022 FIFA World Cup

The twin towers of the Marriott Marquis congress hotel cast long shadows on the Doha Exhibition and Convention Center (DECC), where the Big 5 Qatar construction trade show took place last September...

more
Issue 02/2014 Faymonville

Through the desert sand of the Middle East

For the Faymonville Group, the Middle East has been a white spot on the map for a long time, mainly because the Group had focused on building up networks in such regions as, for example, Eastern...

more
Issue 11/2013 Werner Sobek

FIFA World Cup 2014: Structural design for a new stadium

The new Corinthians Stadium is being built in the Itaquera district of the city of São Paulo, Brazil. The stadium has 65,800 seats; it will be the venue of the opening match of the 2014 FIFA World...

more
Issue 01/2020

Desert rose made of concrete - National Museum of Qatar

The involvement of the Arabian culture is consistent throughout the entire building designed by the French star architect, Jean Nouvel, who was awarded with the 2008 Pritzker Prize, that is often...

more
Issue 10/2014 UBM Sienna

Between FIFA World Cup and Olympic Games

The Concrete Show 2014 took place in Brazil just a few weeks after the final whistle ended the FIFA World Cup, and nearly two years before the Olympic Games. The Concrete Show, on the basis of the...

more