SUBMITTED BY: PAUL MASCHINENFABRIK

Optical inspection of button heads on prestressing steel

Button-headed prestressing tendons are used with end-anchorage for wire tendons in railway sleepers and for poles and towers. Button-headed prestressing wires have two advantages over stranded prestressing tendons: there is no loss of pretensioning force due to wedgeslip and there is, in addition to bonding, an end anchorage through which the tensioning force is applied.

The button heads are produced in series, usually on automatic button-heading machines. Process faults that occur during heading can result in geometric irregularities. Cracks can occur during cold working due to fluctuation in material properties. Use of button-head tendons with faulty button heads can cause failure of the tendon. The exchange of prestressing wire in subsequent processes results in downtimes of the machines,  reworking, and high material consumption.

Solution approach with ­automatic image processing

A camera system with advanced image processing stationed directly downstream of the button-heading machine automatically detects geometrical faults and cracking on the button-heads. The system inspects every head within approx. 10 seconds. During this period, it positions and fixes the prestressing steel, and several cameras take two pictures each with different lighting. Following evaluation of the pictures, faultless button-headed tendons are passed on to the subsequent processes, and faulty button heads are automatically cut off, together with 10 cm of wire, and are disposed of.

The image processing works with very high, constant reliability for optimizing the production process and minimizing reject waste, but does not replace safety-relevant inspection. Material consumption and worktime can be notably reduced.

Related articles:

Issue 2019-05

Pre-stressed concrete structure with galvanized reinforcement

(10) WO 2019/001872 Al (22) 28.05.2018 (43) 03.01.2019 (57) A pre-stressed concrete structure comprises a steel wire or a steel strand. The steel wire or steel strand has been pre-tensioned before...

more
Issue 2018-02 Stainless prestressing steel grades

Ultimate solution for prestressed concrete structures subject to chloride exposure

In the past decades, corrosion-induced damage has repeatedly led to severe component failure in prestressed concrete structures. This is typically caused by inadequate design or poor workmanship,...

more
Issue 2013-05 Schlüsselbauer

New developments in concrete cylinder pipe production

The use of concrete pipes with a steel cylinder on the inside and wire prestressing has been time-tested worldwide for decades, while the production engineering has been hardly developed over a longer...

more
Issue 2013-10

Design of prestressed precast elements in accordance with Eurocode 2

1. Introduction Upon the official introduction of Eurocode 2 (DIN EN 1992-1-1 [1], hereinafter referred to as EC2), several German states, including Bavaria, Hesse and North-Rhine Westphalia,...

more
Issue 2014-05

Corrosion resistant steel strand for prestressed concrete

(11) EP 2 650 431 A3 (22) 14.06.2012 (43) 16.10.2013 (71) Kurosawa Construction Co., Ltd. Tokyo 182-0003 (JP) (84) AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL...

more